10/28/2009
Brockman Hall - Phase I
  • The basement construction is progressing with the exterior walls being sprayed with concrete and followed with a pour concrete wall
  • Recent rainfall has slowed construction of the basement slab, however 30% of the basement structural floor slab has been poured
  • Installation of the new water line along Campanile Road to support this project is nearly complete, with road repairs to be scheduled soon

10/27/2009
Huff House Renovations
  • The permit request has been turned in to the City of Houston
  • Alumni Affairs offices will move beginning Novevmber 4th
  • The Center for Student Professional Development move date is still pending

10/27/2009
South Colleges Renovations and Additions
  • The third floor of the new Baker College wing has been poured and formwork has started on the fourth floor slab
  • The second floor slab for the new Will Rice College wing will be poured October 28th
  • Basement structural supports will be completed this week for the Baker kitchen/servery
  • Roof repairs and temporary waterproofing will be completed this week at the Baker and Lovett ’55 wings

9/30/2009
South Colleges Renovations and Additions
  • The second floor of the new Baker wing has been poured as is visible from College Way
  • Steel for the next set of columns for Baker has already been set
  • The first-floor slab for the new Will Rice wing has been poured to bring that portion of the project out of the ground
  • The chilled water system for the Lovett ’55 wing has been energized
  • Restroom pods will continue to arrive with the second delivery scheduled for Friday, October 2nd

9/29/2009
Huff House Renovations
  • The architect is working on finalizing the exterior design of the southern and eastern sides of building
  • Interior plans will be submitted to the City of Houston for permit soon
  • Construction is anticipated to begin the third week of October
  • Project plans went for permit last week
  • Elevation details are being finalized
  • The office of Alumni Affairs will be relocated the Greenbriar building during construction
  • The temporary re-location of the other building occupant is under way

9/29/2009
Barbara and David Gibbs Recreation and Wellness Center
  • The building officially opened to the public on September 25
  • The competition pool is still on schedule for substantial completion mid-October

9/25/2009
Barbara and David Gibbs Recreation and Wellness Center
  • Grand-opening ceremony scheduled for Friday, September 25, 2009
  • Work on the competition pool is scheduled to complete within two weeks

9/23/2009
Huff House Renovations
  • The architect is working on finalizing the exterior design of the southern and eastern sides of building
  • Interior plans will be submitted to the City of Houston for permit soon
  • Construction is anticipated to begin the third week of October
  • The temporary re-location of the end users is under way

9/18/2009
South Colleges Renovations and Additions
  • The second floor slab for the new Baker wing is scheduled to be poured on Wednesday, September 23rd
  • Next week, the first floor slab for the new Will Rice will be poured
  • The new air units for the ’55 Baker and Lovett wings have been installed
  • The first set of bathroom pods have arrived and are being tested

9/16/2009
Barbara and David Gibbs Recreation and Wellness Center
  • Work on Exterior basketball court is complete
  • Operations and Maintenance training for Rice staff is ongoing
  • Landscaping and irrigation at Competition Pool is scheduled to begin

9/9/2009
Barbara and David Gibbs Recreation and Wellness Center
  • Bulkhead on Competition Pool has been installed
  • Work on Exterior basketball court is ongoing
  • Operations and Maintenance training for Rice staff has begun
  • Temporary Certificate of Occupancy has been achieved

9/1/2009
Huff House Renovations
  • Design development has begun
  • Construction documents are expected to be ready on 9/18/09 and construction is expected to begin the first week of October
  • Current occupants of the building will be moved into alternate locations on campus as construction is underway

8/21/2009
Brockman Hall - Phase I
  • 172 Soldier piles, with a typical depth of 50’, have been finished
  • The entire cap beam is complete
  • Both the drilling rigs have been removed from site
  • The site’s tower crane has been installed
     

8/20/2009
Barbara and David Gibbs Recreation and Wellness Center
  • Striping on the main gym floor is complete
  • Furniture has been installed in the administration building
  • Concrete has been poured for outdoor basketball courts

8/20/2009
South Colleges Renovations and Additions
  • Basement slab for Will Rice will be poured on Friday, August 21st
  • First floor slab for new Baker wing will be poured on Tuesday, August 25th
  • Restroom Pods will start arriving in September
  • Underground work is almost complete
  • Columns have started at the first floor of the new Baker wing
     

8/19/2009
BioScience Research Collaborative Core and Shell
  • Continuing site work in the plaza
  • Continuing installation of lobby finishes and furniture
  • General Contractor is working on punch list items
  • Floor coatings are progressing at the loading dock and valve rooms
  • Plumbing activities continue for tenant improvements
  • Piping work is ongoing in the Rice Institute office on the first floor
  • Sprinklers are being installed in the auditorium, vivarium and lecture hall

8/13/2009
Duncan College
  • O-week advisors have moved into the building
  • Construction crews are finalizing hardscape around the site
  • Freshmen move-in is scheduled for August 16

8/13/2009
McMurtry College
  • O-week advisors have moved into the building
  • Glass is being installed on the McMurtry Commons
  • Construction crews are finalizing hardscape around the site
  • Freshmen move-in is scheduled for August 16

8/6/2009
Barbara and David Gibbs Recreation and Wellness Center
  • Large Oak tree has been moved to accommodate outdoor basketball courts
  • Palm trees have been installed in building courtyard
  • Work has started on outdoor basketball courts
  • Tile work on the competition pool continues

8/6/2009
McMurtry College
  • Temporary Certificate of Occupancy has been issued for the living spaces
  • Construction fences are down and landscaping is near completion
  • Bedroom furniture has been delivered and installed
     

8/6/2009
Duncan College
  • Temporary Certificate of Occupancy has been issued for the living spaces
  • Construction fences are down and landscaping is near completion
  • Bedroom furniture has been delivered and installed
     

7/29/2009
McMurtry College
  • The process of completing final inspections has begun
  • Landscape installation is near completion
  • Furniture installation has begun

7/29/2009
Duncan College
  • The process of completing final inspections has begun
  • Landscape installation is near completion
  • Furniture installation has begun
     

7/24/2009
Barbara and David Gibbs Recreation and Wellness Center
  • Work on the Courtyard hardscape continues
  • Underground piping work on the Competition Pool has begun
  • Exterior brick work is finished
  • Kalwall translucent panel installation is complete
  • Finishes in the Administration Building are complete
  • Installation of the Tectum Panel Suspension System has finished
  • Plumbing and lighting fixtures have been installed
     

7/24/2009
Huff House Renovations
  • Design development has begun
  • Construction documents are expected to be ready the third week of August and construction is expected to begin the first week of September
  • Current occupants of the building will be moved into alternate locations on campus as construction is underway

7/23/2009
South Colleges Renovations and Additions

 

  • The storm water manhole in College Way is almost complete - A storm line from Baker College will eventually drain into this manhole
  • Construction is continuing on the basement walls of Baker College
  • Core Drilling has begun for air conditioning lines in the 1955 wing of Baker College
  • The concrete basement walls are being formed and poured at Will Rice College
  • The electrical line to the Will Rice Commons will be reconnected on July 25th
     

7/23/2009
Pathway to the BioScience Research Collaborative
  • The Pathway to the BRC is substantially complete and ready for pedestrian and minimal cart use
  • Further enhancements to the Pathway will include light fixtures, trash cans, emergency phones and landscaping

7/23/2009
Sewall Hall Accessibility Project
  • Elevator is scheduled to be installed this week
  • Substantial completion is expected on August 13
     

7/7/2009
Brockman Hall - Phase I
  • New utility tunnel is in operation
  • Old utility tunnel has been demolished
  • Building site has been lowered by 6 to 8 feet
  • Soldier piles are going in with 54 of the 172 complete

7/7/2009
South Colleges Renovations and Additions
  • Corners have been set for the new Will Rice wing, and piers are ongoing at the Will Rice basement
  • Piers for the Baker basement have been completed
  • The 100-ton crawler crane has been erected at the Will Rice site
  • Brick and material salvage has begun at 1955 Baker
  • Grade beams for the new Baker wing have begun
  • The project just received the superstructure permits from the City of Houston for the new Baker and Will Rice wings

6/18/2009
McMurtry College
  • Zinc roof continuing
  • Sunshade installation continuing including “sundeck”
  • Interior stair infill complete, stair handrails complete
  • Plaster complete and interior drywall work is continuing in student rooms on the 5th floor
  • Door installation continuing and door hardware installation has begun
  • Cypress siding continuing

6/18/2009
Duncan College
  • Zinc roof continuing
  • Sunshade installation continuing including “sundeck”
  • Interior stair infill complete, stair handrails complete
  • Plaster complete and interior drywall work is continuing in student rooms on the 5th floor
  • Door installation continuing and door hardware installation has begun
  • Cypress siding continuing

6/18/2009
Barbara and David Gibbs Recreation and Wellness Center
  • Recreation pool coping and tile is installed
  • Courtyard hardscape has begun
  • Competition pool floor  has been poured
  • Completed window wall in the lobby
  • Installation of racquetball and squash courts has started
  • Completed drywall finish and continuing paint finishes
  • Air Conditioning Started Up
  • Plumbing fixture installation has started
  • Light fixture installation started

6/11/2009
Brockman Hall - Phase I
  • Excavation of the site has begun
  • Pier drilling and soldier piles are scheduled to begin the week of June 15
  • Increased truck traffic will be apparent on the construction site and surrounding areas – caution should be exercised in these areas

6/5/2009
Barbara and David Gibbs Recreation and Wellness Center
  • Ceramic tile and coping have been installed at the recreation and leisure pool
  • Digging of the competition pool has commenced
  • Metal roofing installation complete
  • Door casings, ceiling grids and ceramic tile installation is complete in the Administration Building
  • The racquetball and squash courts have been framed

6/5/2009
McMurtry College
  • Zinc roof installation continuing
  • Sunshade installation continuing including “sundeck”
  • Interior stair infill continuing
  • Stair handrail installation has started
  • Corner window installation is complete
  • Interior drywall work continuing in student rooms
  • Green roof installation has begun

6/5/2009
Duncan College
  • Zinc roof installation continuing
  • Sunshade installation continuing including “sundeck”
  • Interior stair infill continuing
  • Stair handrail installation has started
  • Corner window installation is complete
  • Interior drywall work continuing in student rooms
  • Green roof installation has begun

6/1/2009
Pathway to the BioScience Research Collaborative
  • Project is still in construction phase
  • Completion is scheduled for July 1st 2009

6/1/2009
Sewall Hall Accessibility Project
  • Project is in demolition phase
  • Elevator installation will begin the week of June 1st
  • Anticipated completion date is August 14th, 2009

6/1/2009
BioScience Research Collaborative Core and Shell
  • Continuing site work in the plaza
  • Cleaning exterior of building
  • Continuing installation of lobby finishes and furniture

6/1/2009
South Colleges Renovations and Additions
  • Baker kitchen/servery has been demolished to the top of the first floor slab
  • New Will Rice is completing interior demolition on June 1, and full building demolition is scheduled for June 2
  • Decorative limestone and other materials have been salvaged from the project buildings
  • Asbestos abatement is beginning the week of June 1st at New Baker
  • Utilities to the South Colleges project have been isolated to minimize future outages to the surrounding area
  • A new gas line has been run to bypass the project to the north of Baker College

5/14/2009
South Colleges Renovations and Additions
  • Site mobilization has commenced
  • Fence placement, tree pruning and removal and other various contractor activities are taking place on site
  • The project team is coordinating with students and Rice staff to with project updates and information

5/13/2009
Brockman Hall - Phase I
  • Tunnel construction is approximately 50% complete and the tunnel utilities have begun to be installed
  • The tunnel is scheduled to be fully complete by June 19th
  • A utility outage is scheduled for May 23 to tie-in the tunnel utilities

5/12/2009
BioScience Research Collaborative Core and Shell
  • Installation of the green roof has commenced
  • Concrete sidewalks are being installed along Travis St. and pavers are being placed along Main St.
  • Tenant improvements continue for Rice Faculty on lab floors three through ten
  • The Rice University classrooms are being built inside the building
     

 

5/7/2009
Duncan College
  • Bracket installation is complete, gutter installation is continuing
  • Zinc roof installation is continuing
  • Interior stair infill has begun
  • Corner window installation has started
  • Masonry installation is complete and wash down is continuing
  • Interior drywall work is continuing in student rooms
  • Green roof installation is continuing
  • Tower cranes have been removed

4/30/2009
Pathway to the BioScience Research Collaborative
  • Design is completed
  • Construction documents will be completed within the next several days
  • Construction will begin the first week of May
  • Anticipated completion is July 1st
     

4/28/2009
Barbara and David Gibbs Recreation and Wellness Center
  • Construction started on the recreation pool on March 30th and work will begin on the competition pool on May 9th
  • Masonry work in the courtyard is near completion
  • Window installation has begun in the MAC gym and the Administration Building
  • Elevator installation has begun
  • Roofing work is near completion

4/28/2009
McMurtry College
  • Bracket installation is complete, gutter installation is continuing
  • Zinc roof installation has started
  • Interior stair installation is complete
  • Window installation is 98% complete
  • Masonry installation is complete and wash down is continuing
  • Interior drywall work is continuing in student rooms
  • Green roof installation has started
  • Volleyball court installation is complete

4/28/2009
Duncan College
  • Bracket installation is complete, gutter installation is continuing
  • Zinc roof installation has started
  • Interior stair installation is complete
  • Window installation is 98% complete
  • Masonry installation is complete and wash down is continuing
  • Interior drywall work is continuing in student rooms
  • Green roof installation has started
  • Volleyball court installation is complete

4/28/2009
BioScience Research Collaborative Core and Shell
  • Installation of the green roof has started
  • Installing concrete sidewalks along Travis and Pavers along Main Street
  • Continuing tenant improvements for Rice faculty on lab floors 3 through 10
  • The Rice classrooms are being built
  • Part 1 of the Vivarium is in for permit

4/22/2009
Huff House Renovations

4/20/2009
Brockman Hall - Phase I
  • Tunnel construction is approximately 40% complete and the tunnel utilities have begun
  • The tunnel is scheduled to be fully complete by June 19th
  • There will be a steam/condensate/chilled water and compressed air outage to Space Science and Hamman Hall the weekend of April 25th in order to install taps and valves in the piping system
  • Concrete has been poured at the entry to the construction site to reduce mud on Campanile Drive

4/17/2009
BioScience Research Collaborative Core and Shell
  • Limestone at the hub base and stair has been completed
  • Curtainwall decorative metal at hub has been installed
  • Rear projection screen in auditorium installed
  • Continuing tenant improvements on for Rice faculty on lab floors 3 through 10
  • The Rice classrooms are being built
  • Part 1 of the Vivarium is in for permit

4/10/2009
South Colleges Renovations and Additions
  • The foundation permit package has been approved by the City of Houston
  • The superstructure permit package has been submitted to the City of Houston
  • Mobilization is planned for the week following Commencement
  • The project team is working to finalize the site utilization plan and parking concerns
  • The project team is meeting with students and Rice staff to communicate the summer and fall work schedule

4/10/2009
Duncan College
  • Bracket installation is continuing, gutter installation started
  • Zinc roof installation has started
  • Interior stair installation is 75% complete
  • Window installation is 98% complete
  • Masonry installation is 98% complete and wash down is continuing
  • Interior drywall work is continuing in student rooms
  • Bucket roof installation is complete
  • Masonry and steel structure complete for the kitchen, server and commons
  • Steel installation is complete for the master house
  • Volleyball court installation is 50% complete

4/10/2009
McMurtry College
  • Bracket installation is continuing, gutter installation started
  • Zinc roof installation has started
  • Interior stair installation is 75% complete
  • Window installation is 98% complete
  • Masonry installation is 98% complete and wash down is continuing
  • Interior drywall work is continuing in student rooms
  • Bucket roof installation is complete
  • Masonry and steel structure complete for the kitchen, server and commons
  • Steel installation is complete for the master house
  • Volleyball court installation is 50% complete

3/30/2009
BioScience Research Collaborative Core and Shell
  • Material/Man hoist was removed the weekend of March 28th
  • Final portions of exterior enclosure are being completed
  • Tenant improvements for Rice faculty on lab floors 3 through 8 are in progress
  • Lobby finishes on floors 1 and 2 are in progress
  • The Rice classrooms are being built
  • Part 1 of the Vivarium is in for permit

3/30/2009
McMurtry College
  • Bracket installation being done in advance of gutter installation
  • Interior stair installation has begun
  • Window installation is 98% complete
  • Masonry installation is 80% complete
  • Interior drywall work started and the mock-up rooms prepared
  • Bucket roof installation has started
  • Masonry and steel structure complete for the kitchen, server and commons
  • Sidewalks and entry ramp at Loop Road have been completed
  • New sidewalk connection at Jones/Brown has been completed

3/30/2009
Duncan College
  • Bracket installation being done in advance of gutter installation
  • Interior stair installation has begun
  • Window installation is 98% complete
  • Masonry installation is 80% complete
  • Interior drywall work started and the mock-up rooms prepared
  • Bucket roof installation has started
  • Masonry and steel structure complete for the kitchen, server and commons
  • Sidewalks and entry ramp at Loop Road have been completed
  • New sidewalk connection at Jones/Brown has been completed

3/27/2009
South Colleges Renovations and Additions
  • The Foundation package has completed the first review with the City of Houston
  • The design team is working to complete an early equipment package and superstructure drawing set for permitting
  • Asbestos abatement work has been done in the basements of Baker College and Will Rice College over Spring Recess
  • Demolition is still scheduled for May following Commencement
  • The project team is meeting with students and Rice staff to prepare for the summer and fall work schedule

3/26/2009
Barbara and David Gibbs Recreation and Wellness Center
  • Construction starts on the recreation pool on March 30th and work will begin on the competition pool on May 9th
  • Masonry work in the courtyard is near completion
  • Window installation has begun in the MAC gym and the Administration Building
  • Elevator installation will begin in April
  • Roofing work is near completion

3/13/2009
Duncan College
  • Steel erection is complete and roofing work has started
  • Windows and exterior masonry are being installed at both colleges
  • Kitchen/Servery structure is complete and roof deck is underway
  • Interior MEP rough-ins and metal stud framing have started
  • Exterior masonry has also started
  • Pod installation is complete
  • Site utilities and site paving are are being installed

3/13/2009
McMurtry College
  • Steel erection is complete and roofing work has started
  • Windows and exterior masonry are being installed at both colleges
  • Kitchen/Servery structure is complete and roof deck is underway
  • Interior MEP rough-ins and metal stud framing have started
  • Exterior masonry has also started
  • Pod installation is complete
  • Site utilities and site paving are are being installed

3/13/2009
BioScience Research Collaborative Core and Shell
  • The second tower crane was removed in mid February
  • The substantial compeletion date for the core and shell work is May 5, 2009 - the date was extended from the end of March by six weeks due to damage sustained from Hurricane Ike
  • The materials hoist will be disassembled at the end of March so that the remaining curtainwall can be completed by May 5, 2009
  • The large tree in the courtyard was planted at the end of February
  • Sitework has commenced and will be complete by May 5, 2009, with the exception of a small portion in the vicinity of the materials hoist
  • The masonry work and the windows are almost complete
  • The main lobby finish work is in progress
  • The service elevator is operational
  • Finishes in the toilet rooms on every floor are nearly complete

3/13/2009
Brockman Hall - Phase I
  • Design development is complete
  • The construction fence has been erected
  • The site has been cleared
  • Relocation of utilities in the area is underway
  • Tunnel excavation has begun

3/13/2009
Rice Village Apartments
  • Obtained Temporary Certificate of Occupancy for tenant move in 
  • Commissioning and punch list work is continuing
  • Landscaping continues around the exterior of the building
  • Several subcontractor trailers will be removed from the site this week, however one trailer will remain for the general contractor

3/13/2009
South Colleges Renovations and Additions
  • 75% Construction Documents have been issued
  • The permitting process has begun with the City of Houston
  • Asbestos abatement work will continue in the basements of Baker College and Will Rice College over Spring Recess
  • Demolition is scheduled for May, following Commencement
  • The project team is progressing on the coordination of demolition, move-out, abatement, and utility work necessary to make the first summer successful

3/10/2009
McMurtry College
  • Steel erection is complete and roofing work has started
  • Windows and exterior masonry are being installed at both colleges
  • Kitchen/Servery structure is complete and roof deck is underway - Interior MEP rough-ins and metal stud framing have started. Exterior masonry has also started
  • Pod installation is complete
  • Site utilities and site paving are are being installed

3/10/2009
Duncan College
  • Steel erection is complete and roofing work has started
  • Windows and exterior masonry are being installed at both colleges
  • Kitchen/Servery structure is complete and roof deck is underway - Interior MEP rough-ins and metal stud framing have started. Exterior masonry has also started
  • Pod installation is complete
  • Site utilities and site paving are are being installed

3/5/2009
Brockman Hall - Phase I
  • Design development is complete
  • The construction fence has been erected
  • The site has been cleared
  • Relocation of utilities in the area is underway
  • Tunnel excavation is scheduled to begin soon

2/27/2009
South Colleges Renovations and Additions
  • 75% Construction Documents have been issued
  • The permitting process has begun with the City of Houston
  • Asbestos abatement work will continue in the basements of Baker College and Will Rice College over Spring Recess
  • Demolition is scheduled for May, following Commencement
  • The project team is progressing on the coordination of demolition, move-out, abatement, and utility work necessary to make the first summer successful

2/27/2009
Barbara and David Gibbs Recreation and Wellness Center
  • The main building is scheduled for air conditioning beginning Apr 27
  • Construction for the competition pool is scheduled to begin on May 9
  • Construction for the recreation pool is scheduled to begin on March 5th upon completion of the courtyard brick
  • The framing of plaster ceilings in the locker room wing continues
  • Interior frame-work and wall installation has now commenced in the Administration Wing
  • Roofing insulation is complete and installed over the multi-purpose gym and weights area

2/23/2009
Barbara and David Gibbs Recreation and Wellness Center
  • Construction for the recreation pool is scheduled to begin on March 5th upon completion of the courtyard brick
  • The framing of plaster ceilings in the locker room wing continues
  • The build-out of the mechanical room near the racquet ball court continues
  • Interior frame-work and wall installation has now commenced in the Administration Wing
  • Roofing insulation is complete and installed over the multi-purpose gym and weights area
  • Block fill on the CMU walls and framing of interior walls is now beginning in the cardio spaces

2/10/2009
South Plant
  • Site preparation has begun with the erection of fencing along the site perimeter
  • Construction activities are scheduled to commence the week of Feb. 23.
  • A large magnolia tree was relocated to the South Plant site
  • The first phase of the project has is under review for permitting by the City of Houston
     

2/5/2009
BioScience Research Collaborative Core and Shell
  • The tower crane is scheduled to be disassembled and removed the weekend of February 13th and the installation of the green roof is will commence at that time
  • The core and shell of the BRC are now scheduled for substantial completion in April 2009
  • Landscape and surrounding hardscape work is expected to be complete by mid May
  • Faculty move in is scheduled to begin in early July and complete by mid August
     

2/5/2009
Sewall Hall Accessibility Project
  • Material ordering is underway and n site work is expected to commence in early May
  • Project is anticipated to complete prior to the start of classes Fall 2009

 

1/26/2009
Rice Village Apartments
  • Punch list work is continuing
  • Landscaping continues around the exterior of the building
  • The temporary fences around the property will be removed later this week
  • Several subcontractor trailers and connex boxes will be removed from the site this week, however one trailer will remain for the general contractor

1/26/2009
Barbara and David Gibbs Recreation and Wellness Center
  • Brick work and window frame installation at the pool courtyard has begun
  • The locker-room area will be “dried-in” within the next few weeks
  • Electrical overhead and fire sprinkler rough-in  for the second floor of the locker-room wing will take place over the next several weeks
  • Mechanical, electrical and plumbing rough-in continues on the second floor
  • Interior gyp wall framing and plaster ceiling framing is ongoing in the locker room wing
  • Electrical panel rooms and the build out of the mechanical room is underway at the administration and racquet ball court area
  • Detailing and roof decking is taking place at the atrium between the administration building and the racquet ball court space
  • Detail and metal roof decking is ongoing at the MAC Gym and cardio space
  • Roofing insulation and ice and water shield will begin in the next few weeks
  • Steel stairs are begin erected at the multi-purpose and cardio area
  • CMU walls at 2nd floor are being installed over the next several weeks
  • Fireproofing of the mezzanine will be complete within three weeks
  • 211 days remaining until the grand opening

1/26/2009
McMurtry College
  • Work on the fifth floor has commenced; steel beams and CMU walls are being installed
  • Windows are being installed on site at both colleges
  • Second floor work at the Kitchen/Servery is well underway and the libraries and private dining rooms for both colleges are taking shape
  • Exterior brick work on the exterior has begun and is making terrific progress
  • Mechanical, electrical and plumbing rough-in continues at both colleges
     

1/26/2009
Duncan College
  • Work on the fifth floor has commenced; steel beams and CMU walls are being installed
  • Windows are being installed on site at both colleges
  • Second floor work at the Kitchen/Servery is well underway and the libraries and private dining rooms for both colleges are taking shape
  • Exterior brick work on the exterior has begun and is making terrific progress
  • Mechanical, electrical and plumbing rough-in continues at both colleges
     

1/9/2009
Brockman Hall - Phase I
  • Site preparation and construction is scheduled to commence the week of Feb. 23.
  • One large tree and several smaller trees will be relocated to the South Plant within the next two weeks
  • Design continues on the project and the first phase of the project has been sent to the City of Houston for permitting
     

 

1/9/2009
South Colleges Renovations and Additions
  • Construction drawings are 50% complete
  • Asbestos abatement has commenced in critical areas
  • The project team continues to exam ways to repurpose building materials to incorporate in the new building construction
  • Construction is still expected to begin May 2009
     

12/28/2008
South Plant
  • Project is substantially complete.
  • Full utility connections to CRC have been made.
  • The tower glass has been installed
  • The scaffolding will be disassembled in early January
  • A lighting mock-up will be visable during January
  • Several relocated trees will arrive on site during the winter recess

12/28/2008
Brockman Hall - Phase I
  • Three large trees from the future site for the Brockman Hall for Physics
  • The trees will be relocated to the South Plant close to Entrance 4
  • Construction will begin mid to late February
     

12/26/2008
Barbara and David Gibbs Recreation and Wellness Center
  • The metal roof-deck is being installed in the locker room wing
  • The second floor decking is complete and the concrete has been poured as well at the Administration Building wing
  • The mechanical equipment for the first floor has been delivered and placed
  • The mechanical duct rough in overhead for the second floor near the racquet ball courts has begun and should complete by January 8
  • Electrical wall and overhead rough in has begun on the first floor
  • Steel erection has begun at the southwest MAC gym and should be complete by January 7
  • CMU walls on the first floor near the cardio/weight area are being assembled and installed
  • Roof framing at two story entry atrium has begun

12/8/2008
Anderson Biology Roof Replacement
  • Contactors have removed more than half of the roof and work is proceeding towards the west-end of the building near the Greenhouse
  • The demolition of the old roof should be complete within the next several days, barring extreme weather conditions
  • The second-layer roof and new flashing cap around the perimeter of the building will commence as soon once demolition is complete
  • Work is expected to complete in January
     

12/2/2008
BioScience Research Collaborative Core and Shell
  • The work associated with the exterior wall enclosure, curtain-wall, windows and brick is nearly complete
  • Mechanical, electrical, plumbing and fire protection rough-in is close to completion
  • The core and shell are scheduled to be substantially complete in March of 2009
  • Work for tenant improvements began in October of 2008

12/2/2008
Oshman Engineering Design Kitchen
  • Office doors have been installed and painting is complete
  • Data and power floor boxes have been installed in the assembly space
  • All furniture and equipment has been delivered and installed to the site
  • The pervious concrete sidewalk, permanent handrails and interior lighting have been installed
  • The green-roof is installed

 

12/2/2008
South Plant
  • Project is substantially complete
  • Full utility connections to CRC have been made
  • Glazing of tower should be completed in early December
  • Punchlist items are being addressed

12/1/2008
McMurtry College
  • Block work on level five of both colleges is ongoing
  • Section six of the fifth floor has been poured and section seven will be poured the week of December 1
  • The west-half of the Kitchen/Servery second-floor slab has been poured
  • The second floor wall construction for the Kitchen/Servery is proceeding
  • Mechanical, electrical and plumbing rough-ins of both colleges are ongoing for floors one through three
  • Steel construction has begun
  • Exterior brick work will commence early December

12/1/2008
Duncan College
  • Block work on level five of both colleges is ongoing
  • Section six of the fifth floor has been poured and section seven will be poured the week of December 1
  • The west-half of the Kitchen/Servery second-floor slab has been poured
  • The second floor wall construction for the Kitchen/Servery is proceeding
  • Mechanical, electrical and plumbing rough-ins of both colleges are ongoing for floors one through three
  • Steel construction has begun
  • Exterior brick work will commence early December

11/25/2008
Rice Village Apartments
  • The building roof completed August 10th
  • Brick has been delivered to the site
  • Rough-in cabling is complete on the fourth and third floors for IT and fire alarm
  • The corridor concrete pours continue and the fourth floor will be poured soon
  • Cabinets for the fourth floor are nearly done
  • Laminate for the fourth floor is significantly finished
  • The elevator is expected to be delivered to the site within the next week
  • Building interiors and finishes are ongoing
  • MEP work continues to take place throughout the building

11/24/2008
Rice Village Apartments

11/24/2008
Barbara and David Gibbs Recreation and Wellness Center
  • The underground chilled-water taps and vault installation is underway and will complete by December 11th
  • Steel erection is ongoing through December 8th
  • Plumbing risers are being installed and mechanical ducts rough-in are going in the overhead on the first floor
  • Concrete masonry unit wall installation is ongoing on the first floor through December 18th
  • The concrete forms and pours for the second floor bridge from the lobby to the administration building will begin within the next week
  • Steel erection for the administration building will complete by December 2nd
  • The composite columns for the basket ball courts on the second floor will complete by December 5th

11/20/2008
Tudor Fieldhouse and Youngkin Center
  • Opening of Tudor Fieldhouse was successful
  • First games have been played
  • Minor punch-list items will continue now that the building is operational
     

11/12/2008
Anderson Biology Roof Replacement
  • Contractor is on site and work has commenced
  • Roof curbs are being removed
     

11/7/2008
Tudor Fieldhouse and Youngkin Center
  • Work is focused on the first home basketball game on November 15
  • All brick installation is complete
  • Furniture installation is complete
  • Tree relocation is complete
  • The center-hung scoreboard installation is complete and being tested

11/5/2008
Rice Village Apartments
  • The building roof completed August 10th
  • Brick has been delivered
  • Rough-in cabling is complete on the 4th and 3rd floors for IT and fire alarm
  • The corridor concrete pours continue and the fourth floor will be poured soon
  • Cabinets for the fourth floor are nearly done
  • Laminate for the fourth-floor is significantly finished
  • The elevator is expected to be delivered to the site within the next week
  • Building interiors and finishes are ongoing
  • MEP work continues to take place throughout the building

 

10/29/2008
Tudor Fieldhouse and Youngkin Center
  • All brick installation is complete
  • Furniture installation is roughly 40% complete and scheduled to be complete by November 6
  • Tree relocation is complete
  • The center-hung scoreboard installation will be complete early next week
  • The north-plaza brick pavers installation is complete and the sidewalks on north and east side of building to will be completely installed by November 3
  • The striping of the court has had its first court of finish and the interior bleacher seating is complete
  • Restroom partitions are scheduled to begin installation on October 31 and interior painting will complete by November 5

10/27/2008
Anderson Biology Roof Replacement
  • Contractor will be on site November 3rd
  • Cold tar application does not require the use of a hot-tar kettle, however some tar odor will still be present
  • The loading dock roof-deck will not be roofed during this project
     

10/27/2008
McMurtry College
  • Block work on levels four and five of both Duncan and McMurtry Colleges is ongoing and framing on the fifth floor of both colleges is proceeding
  • Duncan College section seven of the fourth-floor has been poured and the fifth floor section one will be poured late this week
  • McMurtry College fourth-floor sections five and six have been poured and section seven and fifth-floor section 1 will be poured this week
  • The west-half of the Kitchen/Servery is being formed for the second-floor slab
  • The exterior wall framing for the Kitchen/Servery second level is proceeding
  • Mechanical, electrical and plumbing rough-ins of McMurtry and Duncan Colleges are ongoing for floors one through three
  • Steel for the site is anticipated to begin arriving mid-November
  • Masonry work will commence mid to late November

 

10/27/2008
Duncan College
  • Block work on levels four and five of both Duncan and McMurtry Colleges is ongoing and framing on the fifth floor of both colleges is proceeding
  • Duncan College section seven of the fourth-floor has been poured and the fifth floor section one will be poured late this week
  • McMurtry College fourth-floor sections five and six have been poured and section seven and fifth-floor section 1 will be poured this week
  • The west-half of the Kitchen/Servery is being formed for the second-floor slab
  • The exterior wall framing for the Kitchen/Servery second level is proceeding
  • Mechanical, electrical and plumbing rough-ins of McMurtry and Duncan Colleges are ongoing for floors one through three
  • Steel for the site is anticipated to begin arriving mid-November
  • Masonry work will commence mid to late November

10/27/2008
Barbara and David Gibbs Recreation and Wellness Center
  • The underground chilled-water installation is ongoing and scheduled to complete November 4th
  • Chilled-water taps/vault installation has commenced and is anticipated to complete by December 11th
  • The plumbing risers in the locker room wing on the first floor have been installed
  • Mechanical duct and electrical rough-in overhead is ongoing on the first floor of the locker room wing
  • Plumbing distribution equipment and CMU wall installation is scheduled to begin in that area on November 3rd
  • The second floor concrete bridge from the lobby to the Administration building has been formed and will be poured this week
  • CMU wall installation will commence at the first floor near the racquet-ball courts on November 11th
  • Steel erection has begun on site
     

10/22/2008
Barbara and David Gibbs Recreation and Wellness Center
  • Installation of underground chilled-water lines is complete
  • Installation of chilled-water taps and vault are scheduled to complete by November 7th
  • The second floor slab pour for the locker room wins is complete
  • The second floor column forms are being formed and the first floor plumbing risers were being installed
  • The first floor grade beams and columns are complete at the racquet-ball and squash courts and the second floor over the courts has been poured
  • Steel erection in this area began on October 14
  • The second floor concrete has been poured in the southwest MAC Second floor concrete slab is complete and the second floor columns have been poured
  • The forming and placing of rebar for the multi-purpose cardio area at the mezzanine level is complete - Second floor columns are being formed in that area as well

10/20/2008
Tudor Fieldhouse and Youngkin Center
  • Brick installation is complete at Autry Court and for the north addition
  • Brick installation on the north face of the two story building is 95% complete
  • Exterior and interior soffit-plaster ceilings activities are ongoing throughout the project and are 50% complete
  • The window wall framing for the main entrance to the arena is currently underway
  • The terrazzo flooring installation is complete in the lobby area directly outside of the main arena
  • Ceramic tile installation has begun in the corridors of Autry Court and new restrooms
  • Elevator installation is 90% complete
  • The current Recreation Center offices, weight room and dance studio have been relocated and existing spaces are 95% demolished
  • Underground utilities in Autry Court are 98% complete and mechanical, electrical, and plumbing trades are roughing-in lines in walls and ceilings throughout the building
  • The new scoreboard for the arena has been installed will be operational in two weeks
  • Concrete curb work has begun along College Way in front of Autry Court

10/17/2008
South Colleges Renovations and Additions
  • The project is currently in the design development phase
  • Construction Documents will be completed in early spring of 2009
  • Construction will commence in May of 2009 and be substantially complete in July of 2010

10/10/2008
Rice Children's Campus
  • Rice Children’s Campus officially welcomed children to the first day of class on September 29
  • The building was constructed using green building practices to meet LEED standards and will be among only a handful of LEED-certified schools in Texas
  • The green features include: An 8,000-gallon, underwater rain-harvesting tank that collects water that will be used to irrigate the native trees and plants designed by landscape architect Harry Dill, a roofline designed with a unique angle to flood the classrooms with natural light, odor-free and zero volatile organic compound paints and other materials, and a self-monitoring mechanical system to maximize energy efficiency
  • The building used reclaimed materials from the old houses  that were carefully deconstructed to make way for the facility - 10,000 of those bricks were incorporated into the façade of the children's campus

10/8/2008
South Plant
  • Start-up and commissioning activities are ongoing
  • The glazing of the tower glass began on September 27th and is scheduled to compete late November
  • Installation of the air inlet hood for the tunnel just north of the South servery is scheduled for last week in October
  • Final cleaning of the tunnel system for turnover to Rice is underway and should complete the second week of October
  • A temporary metal fence has been installed atop the berm-wall
  • Painting of exposed exterior piping is underway
  • Pedagogical display monitors and security cameras have been installed
  • The project team is working with the Recreation Center to re-install the Frisbee-golf course in the detention area - This should occur in mid to late October
  • The green construction fence on the Intramural Field 7 field will be replaced with a permanent outfield fence the first week of November
  • The South Plant has been supporting the EEB with assistance in planting of native flowers in detention - This planting is expected to occur in late October
  • The gate arms on Alumni Drive will be repaired within the next several weeks
  • Installation of IT and telecommunication conduits and fiber through the tunnel system has commenced
  • Completion of tie-ins to Collaborative Research Center are still on-hold pending the electrical street crossing resolution
  • Current estimated date for complete site demobilization is December 5, 2008

9/26/2008
McMurtry College
  • Block work is ongoing at Duncan and McMurtry Colleges on level three and will progress to level four in the next few weeks
  • Concrete is being poured at Duncan College at level four
  • Bathroom pods continue to be delivered to the site and are being installed in the student rooms
  • Mechanical, engineering and plumbing rough-in continues throughout both McMurtry and Duncan Colleges
  • The foundation at McMurtry College is being set
     

9/26/2008
Duncan College
  • Block work is ongoing at Duncan and McMurtry Colleges on level three and will progress to level four in the next few weeks
  • Concrete is being poured at Duncan College at level four
  • Bathroom pods continue to be delivered to the site and are being installed in the student rooms
  • Mechanical, engineering and plumbing rough-in continues throughout both McMurtry and Duncan Colleges
  • The foundation at McMurtry College is being set
     

9/9/2008
McMurtry College
  • Block work continues at the Kitchen/Servery
  • The second floor at the Kitchen/Servery has been poured
  • Electrical rough-in for the Kitchen/Servery roof is ongoing
  • Underground ductwork was completed and foundations and grade-beams for the north-side of Duncan College were poured—the south side has been poured as well
  • Bathroom pods continue to be delivered to the site and installed into student rooms
  • Duncan College fourth-floor section one and two are scheduled to be poured on Wednesday and Saturday of this week

 

9/3/2008
Brockman Hall - Phase I
  • This project is currently in the design phase

9/2/2008
Rice Children's Campus
  • The building is ready to be occupied
  • The contractor is finalizing all punch list items
  • Metropolitan Montessori System is in the process of moving into the building
  • All landscaping will be complete this week

8/28/2008
Rice Village Apartments
  • The building roof completed August 10th
  • Building wrap is completed and the hardi-plank installation is 75% complete on the north side
  • The 4th floor has been inspected by the city and drywall is starting on the ceiling
  • Brick has been delivered
  • Rough-in cabling is complete on the 4th and 3rd floors for I.T. and fire alarm
  • Drywall is staged in every suite and protected with plastic sheeting

8/28/2008
BioScience Research Collaborative Core and Shell
  • The CRC shell and core is approximately 65% complete. 
  • The target Substantial Completion Date remains March of 2009. 
  • The curtainwall and brickwork has commenced. 
  • The steam and chilled water piping under University are intalled.
  • The electrical service under University is currently being installed.

8/27/2008
Tudor Fieldhouse and Youngkin Center
  • Brick installation is complete on Autry Court and the North Addition
  • Brick installation on the North face of the two story building is 60% complete
  • Pouring of the concrete stairs for the west and east side main stairs will begin within the next few weeks
  • Installation of window-wall-frames is ongoing at the main entry to the arena and the administration building on the north side
  • Terrazzo flooring installation will begin in two weeks
  • Ceramic tile installation has started in the corridors of Autry Court and new restrooms.
  • Drywall installation is 90% complete throughout the building
  • Underground utilities in Autry Court are 98% and the elevator installation is on going
  • Reroofing of Autry Court is ongoing and 80% and will complete within the next few weeks – weather depending
  • The steel erection and the roof for the temporary building is complete
  • Drawings for the Ley Plaza have been submitted for city approval

8/26/2008
Oshman Engineering Design Kitchen
  • Metal panels and glass for the shadow box window at the machine shop are being installed
  • Office doors are being installed and painting is almost complete
  • Data and power floor boxes are being installed in the assembly space
  • The pervious concrete sidewalk will installed this week
  • Furniture and remaining equipment will begin to be delivered and installed on September 2nd
  • The basement wall repairs in the back hallway will begin the first week of September
  • All final details in the mechanical and electrical rooms will be complete within the next few weeks
  • Permanent handrails and interior lighting will be installed the week of September 2nd
  • The green-roof will be installed in October

8/24/2008
Barbara and David Gibbs Recreation and Wellness Center
  • The under-ground-chilled water lines installation continues
  • Installation of chilled-water taps will begin early September
  • The first floor columns in the locker room area are continuing to be poured
  • The seal slab at the pool equipment pump room will begin next week
  • The structural slab for the administration area and racquet ball courts will continue to be poured through the first week of September
  • The first floor columns at the MAC gym and cardio and weights area will continue through the end of August

8/21/2008
BioScience Research Collaborative Core and Shell
  • The CRC superstructure topped out in March of 2008
  • The work associated with the exterior wall enclosure, curtainwall, windows and brick, has commenced
  • Mechanical, electrical, plumbing and fire protection rough-in has begun
  • The core and shell is scheduled to be substantially-complete in March of 2009
  • The tenant work is scheduled to begin this August, 2008

8/21/2008
South Plant
  • Alumni Drive is re-opened to traffic.
  • All remaining construction trailers have been relocated inside the South Plant utility yard and landscaping of the surrounding area has begun
  • The first boiler has been fired-up and the geothermal air conditioning system is operational
  • The emergency generators were started and tested successfully and were quieter than anticipated
  • The first chiller was started and produced chilled water – the second chiller is due to be started the week of August 4th
  • A steam blow is anticpated for the week of August 25th

8/21/2008
Rice Children's Campus
  • Commissioning is ongoing
  • Landscape materials are being installed
  • Furniture is being placed inside the building
  • City of Houston storm-sewer project on Chaucer Street is complete
  • Final punch-list items are being corrected

8/17/2008
McMurtry College
  • McMurtry College third-floor sections five and six and Duncan College third-floor sections six and seven were poured
  • Block work continues at the Kitchen/Servery and the wall for the pizza oven has been poured
  • Deck work and electrical rough-in for Kitchen/Servery roof is on-going
  • Underground ductwork was completed and foundations and grade beams for the north side of Duncan Commons were poured – the south-side will be poured next week

8/17/2008
Duncan College
  • McMurtry College third-floor sections five and six and Duncan College third-floor sections six and seven were poured
  • Block work continues at the Kitchen/Servery and the wall for the pizza oven has been poured
  • Deck work and electrical rough-in for Kitchen/Servery roof is on-going
  • Underground ductwork was completed and foundations and grade beams for north side of Duncan Commons were poured – the south-side will be poured next week

8/17/2008
"The 'John and Anne' Grove"
  • The fences are gone and the Grove is open
  • The last of the sod has been brought to the site and installed
  • Additionally, azaleas and a new live oak were planted
  • The planting at the south end of the site is completed
  • Some remaining work remains and this includes; additional work on some drain inlets, adjustments to target of three light
  • Come by and take a walk in this lovely area

8/17/2008
Barbara and David Gibbs Recreation and Wellness Center
  • Underground Chilled Water Lines are in process of being installed on-site
  • The grade beams for the locker room wing are being formed
  • The first floor columns in the locker room wing will be poured within the coming week
  • The seal-slab at the pool equipment pump room will be poured soon
  • The grade beams for the racquetball courts are anticipated to be poured within the next weeks
  • The first floor columns for the cardio and weights area is ongoing through the end of August
  • The second floor forms are ongoing for this area throughout the week
  • Rebar will be place on the second floor of this space as well

8/14/2008
Oshman Engineering Design Kitchen
  • Building commissioning is ongoing
  • Doors and interior window frames have all been installed
  • Installation of the exposed ductwork and the painting of the interior has begun
  • The interior glass installation began this week
  • The basement where the MOB (band hall) meets is being cleaned up
  • The HC ramp is being constructed and installed at the west entrance
  • Installation of exterior pervious concrete sidewalks will begin within the coming weeks
  • Installation of new furniture and moves from Ryon Lab will begin on September 2nd as well as the installation of exterior landscaping

8/13/2008
Barbara and David Gibbs Recreation and Wellness Center
  • The final waterline connection for the site is in progress
  • The underground chilled water line installation begins next soon
  • In the locker-room wing the structural slab is being formed and placement of reinforced steel is ongoing
  • Plumbing sleeves are also being placed in this area and the second floor columns are being formed
  • The site entrance at Alumni Drive has been reopened
  • Foundation beams are being formed at the Administration Building
  • The electrical underground is ongoing and the first floor concrete slab is complete
  • The foundation beams have been poured at the wet-classroom area
  • In the multi-purpose room and cardio area the sanitary and electrical underground lines are ongoing

8/13/2008
Tudor Fieldhouse and Youngkin Center
  • Brick installation is 90% complete on Autry Court
  • Scaffolding is being constructed for masonry activities in front of the new Administration building
  • Drywall installation is 80% complete throughout the building
  • The interior demolition of Autry Court is 90% complete and underground utilities are 98% complete
  • Painting of the Autry Court Bowl ceiling is taking place this week while the Recreation Center is closed
  • Installation of the new south bleachers is complete
  • Re-roofing of Autry Court is ongoing and 60% complete
  • Foundation piers and grade beams are complete for the temporary building behind Autry Court and the concrete slab will be poured this week
  • Landscape retaining walls and the concrete slab for the plaza in front of Autry Court are complete
  • The Recreation Center will be closed August 1 – August 17 for routine maintenance
  • Exterior window frames and glazing will begin in two weeks and ceramic tile installation will begin soon

8/6/2008
Oshman Engineering Design Kitchen
  • Installation of exterior windows and doors is ongoing over the coming weeks
  • Interior walls are being painted and carpet is being installed in the meetings rooms and computation space
  • Within the next few weeks the electrical wiring and installation of floor boxes will be completed and the data and a/v systems will be installed
  • The HC ramp is being constructed and installed at the west entrance
  • The exterior paving and pervious concrete is being poured over the next several weeks
  • Building commissioning is ongoing
  • Installation of new furniture and moves from Ryon Lab will begin on September 2 as well as the installation of exterior landscaping

1/1/1900
Huff House Renovations

The Construction Information Center at Rice University is located at the corner of College Way and Alumni Drive.

Monday-Friday, 9 a.m.-5 p.m.
713-348-3793